Contractor phone estimates usually price walls, finishes, and fixtures. They rarely include ADA path-of-travel upgrades, Title 24 energy documentation, structural review for wall openings, health-department kitchen requirements, or permit fees. In San Diego those line items can add 15 to 30 percent to a naive estimate.

What does a commercial TI cost per square foot in 2026?

Space type$ / sf (2026)What that range assumes
Basic office$40 – $90Paint, carpet, minor MEP; reuse partitions
Standard office (Class B/C)$90 – $175Reconfigured walls, new finishes
High-end office (Class A)$175 – $325Custom millwork, upgraded MEP, AV
Medical / dental office$150 – $350Specialized plumbing, gas, ADA
Retail — second-generation$85 – $200Reuse of existing storefront and MEP
Retail — new / premium$150 – $300New storefront, branded finishes
Restaurant — second-generation$200 – $400Existing hood and grease trap; refresh
Restaurant — full buildout$300 – $500+New hood, grease interceptor, health
Warehouse / industrial$25 – $70Racking, dock, minor office; light MEP

San Diego–specific office bands often cluster around $100–$180 per square foot. City of San Diego tenant-improvement permit and plan-check fees for a 4,000 sf office commonly land around $6,000–$9,000 combined. Title 24 documentation is typically $1,500–$4,500 when lighting, HVAC, or envelope is modified.

How long does a San Diego TI actually take?

Landlords often offer 60–90 days of rent abatement sized for a fast permit. Most TIs need 90–180 days from lease signing to occupancy. The gap is rent paid on a space you cannot use — which is why an architect walkthrough before the lease is signed is the highest-leverage hour on the project.

PhaseTime bandNotes
Design and construction documents4 – 10 weeksDepends on complexity
City plan check — first review3 – 6 weeksSan Diego DSD target is shorter; actuals vary
Correction cycles (usually two)2 – 6 weeks eachHalf of projects need more than two
Health department (restaurants)3 – 8 weeksRuns parallel with city review
Construction — mid-range office6 – 14 weeksReconfigured walls, new finishes
Construction — restaurant TI16 – 30 weeksKitchen, hood, grease, health inspections

What Nalu Architecture Inc. does — and does not claim

We coordinate independent structural, MEP, and Title 24 consultants so the drawing set is internally consistent. We do not claim first-cycle plan-check approval; nobody honestly can. We do produce a set a reviewer can read, and we respond to corrections in writing. Nalu is the architect, never the general contractor.

Related: commercial services.

Questions we hear

Download the full PDF Start a conversation More San Diego architecture questions

NALU® is a registered trademark of Nalu Architecture, Inc. Architectural services are provided through Chris Schumm, AIA, California Registered Architect, License No. C-36569. This page is general planning information for 2026, not an opinion on a specific site. Every engagement is scoped and contracted individually.